How to Reboot or Power Down an NEC SV8100 SystemPlease follow the guide below for instructions on how to reboot or power down an NEC SV8100System.Power ButtonThe power switch is located on the front of the SV8100 chassis to the left hand side.The SV8100 can support up to a total of 4 Chassis. If you have more than one chassis then theymust be turned off and on again in a certain order. Please see image below of what the systemwill look like it if it is a standalone system or if there are multiple chassis.Power switches are located in the same location for all Chassis’.Reboot/Power Down for Single Chassis SystemIn the event of a reboot or complete power down, if you only have a single chassis, pleasefollow the instructions below.1. Press the power switch to the off position2. The system will power down, leave the system powered off if required (Due to electricalwork being carried out)3. Alternatively, count to 10 and then press the power switch back to the on position4. The system should be up and operational within 5 minutes.Reboot/Power Down for 2 Chassis SystemIn the event of a reboot or complete power down, if you have 2 chassis’, please follow theinstructions below.Power switchSingle Chassis System Two Chassis System Four Chassis System