POST INSTALLATION CHECKIf manual by-pass valves have been installed at the solenoid valves (Figure 1, Item 9), they should be openedto allow checking the system for leakage before the electrical check out. The pumps should be set to operateat normal pressure (500 psi maximum), and oil drawn from each dispensing point. When it is certain that allair and foreign materials have been purged from all lines, the piping system should be checked for leaks. Theby-pass valves should be closed before proceeding with the electrical check out.Operational Check1. Double check all electrical connections for correctness and possible shorts and opens.2. Turn on the circuit breaker for the console to be checked (it is suggested that only one system be checkedat a time.3. Follow the Normal Operation procedure below, being sure to enter a large amount for this trial run.4. Rotate the Station Selector switch to each position. Stop at each position and make sure the solenoid .......valve and the remote “Ready” light for the station selected is on. Check to make sure no station is enabled ....other than the one selected. Also make sure the air pump is activated for the product associated with .......theunit being checked out. As each station is enabled and the lines pressurized, check for leaks. NOTE: Leakagenot only causes a mess and a loss of product but it will also cause erroneous control of the ......amount of theproduct delivered.5. As each station is checked out, draw some fluid from each line to make sure that the lines are free of air ...pockets. Also make sure it is the correct fluid.6. Now that the lines are clear of air, dial in an appropriate amount of fluid and check the accuracy of deliveryof each type of fluid.It is suggested that when the check out is complete, that the consoles and their associated circuit breakers belabeled by fluid type.OPERATION INSTRUCTIONSIt is strongly recommended that this system not be considered fully operational until the “POSTINSTALLATION CHECK” has been completed. Once the circuit breakers controlling the power tothe system are turned on, all operations are controlled from the console.CAUTION!Normal Operation1. Turn power key lock switch to ON.2. Set Station selector dial to desired setting.3. Push “SET”; “SET ACTIVE” light should come on.4. Push “SELECT”; the far right digit will flash. Adjust the digit value using the up arrow. Push “SELECT” to ...move to the next digit. Repeat these steps for all required digits.5. When completed, push “SET”. “READY” light should come on and stay on for the delivery.6. Dispense fluid.7. If the entire amount is not dispensed, press “ZERO” to zero the count.10