TESTING YES/NO DATE TO BECOMPLETED1. The cooling tower fan has been checked for blade pitch andproper operation.2. The chilled water and condenser water lines have been:a. Filledb. Testedc. Flushedd. Ventede. Strainers cleaned3. The chilled water and condenser water pumps have beenchecked for proper rotation and flow.4. The following cooling load will be available for start-up:a. 25%b. 50%c. 75%d. 100%5. The refrigerant charge is at the machine.6. Services such as electrical power and control air will be avail-able at start-up.7. The electrical and mechanical representatives will be availableto assist in commissioning the machine.8. The customer’s operators will be available to receive instruc-tions for proper operation of the chiller after start-up.Concerns about the installation/request for additional assistance:I am aware that the start-up time for a Carrier chiller can take between 2 and 6 days depending on the model of the machine andthe options and accessories used with it.Your contact at the jobsite will bePhone numberBeeper numberFax numberIn accordance with our contract, we hereby request the services of your technician to render start-up services per contract termsfor this job on (Date). I understand that the technician’s time will be charged as extra services due to correcting itemsin this checklist that are incomplete.Signature of PurchaserSignature of Jobsite Supervisor- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -CUT ALONG DOTTED LINE CUT ALONG DOTTED LINECopyright 1997 Carrier CorporationManufacturer reserves the right to discontinue, or change at any time, specifications or designs without notice and without incurring obligations.Book 2Tab 5aPC 211 Catalog No. 531-940 Printed in U.S.A. Form 19XR-2SI Pg CL-2 10-97 Replaces: 19XR-1SI