PSD-QS (02/16) Page 404) Final Charge1. Remove the Schrader core tool from the hose just taken off of the initial charging port.2. Crack open the LP valve on the manifold gage set so that a small amount of refrigerant gasflows to purge the hose. Connect the hose to the final charging port, shown in Figure 28.Tighten the hose to the final charging port and turn off the LP valve when the hose connectionis secure.3. Start the system in heat mode. Disconnect the control wire from the “O” terminal to ensurethe system remains in the heat mode during the final charging process. In an air system, thedesign (and minimum) air flow is 400 cfm per nominal ton. In a hydronic system, the design(and minimum) circulating water flow to 3 pgm per nominal ton. As installed, higher thandesign air and circulating water flows are acceptable, recognizing that this will cause greaterpower consumption by the air handler and circulating pump motors.4. Slowly open the LP valve on the manifold gage set and add refrigerant just fast enough tomaintain the suction pressure.5. Slowly add refrigerant until liquid refrigerant is clearly seen in the middle sight glass of theACC, as shown in Figure 29.6. Shut the LP valve on the manifold gage set and run the system for 20 minutes to ensure thatthe refrigerant liquid level remains at the middle slightly glass. If the liquid refrigerant leveldrops below the middle sight glass during this time, slowly add refrigerant until the liquid levelstabilizes at the middle sight glass.7. With the liquid refrigerant level at the middle sight glass, attach and insulate a temperatureclamp or probe securely to the earth loop vapor line at the compressor unit service valveshown in Figure 28. Read the measured temperature. Also read the LP gage pressure on themanifold gage set. Use a pressure/temperature chart (Figure 31) to verify that the system isoperating at saturation, meaning that no superheat is measured on the earth loop vapor line.To verify this, the measured vapor line temperature should be within ± 3°F of the saturationtemperature read from the chart for the measured LP gage pressure. If the measuredtemperature is out of this range, contact ETI technical support at 1/863-701-0096.8. After verifying that the system is operating at saturation in heating mode, and with thesystem still operating in heating mode, slowly open the LP valve on the manifold gage set,and slowly add refrigerant to the system until the refrigerant liquid level is at, but notabove, the top ACC sight glass, as shown in Figure 30. At no time should the refrigerantliquid level be above the top ACC sight glass.9. The system is now fully charged. Document the weight of the refrigerant charge in thesystem. Write it down on the Warranty Registration Card and inside the compressor unit onthe electrical diagram, for future reference.10. Re-connect the control wire to the”O” terminal. The system is now operational in heating andcooling modes.