1710. InstallationNote: Do not use the wall receptacle as the input power source for the UPS, as itsrated current is less than the UPS’s maximum input current. Otherwise the receptaclemay be burned and destroyed.4) Connect the input and output wires to the corresponding input and outputterminals according to the following diagram.Note: you must make sure that the input and output wires and the input and outputterminals are connected tightly.5) The protective earth ground wire refers to the wire connection between theequipment which consumes electric equipment and the ground wire. The wirediameter of protective earth ground wire should be at least as above mentionedfor each model and green wire or green wire with yellow ribbon wire is used.6) After having completed the installation, make sure the wiring is correct.7) Please install the leak current protective breaker at the output power distributionpanel of the UPS if necessary.8) To connect the load with the UPS, please turn off all the loads first, then performthe connection and finally turn on the loads one by one.9) No matter the UPS is connected to the utility power or not, the output of the UPSmay have electricity. The parts inside the unit may still have hazardous voltageafter turning off the UPS. To make the UPS have no output, power off the UPS,and then disconnect the utility power supply.10) Suggest charging the batteries for 8 hours before use. After connection, turn theinput breaker in the “ON” position, the UPS will charge the batteries automatically.You can also use the UPS immediately without charging the batteries first, butthe backup time may be less than the standard value.11) If it is necessary to connect the inductance load such as a monitor or a laserprinter to the UPS, the start-up power should be used for calculating the capacityof the UPS, as its start-up power consumption is too big when it is started.Input and output Terminal Block wiring diagram of6000H(XL)/10000H(XL)