4-3 Setting up & Commissioning514C Product ManualBASIC SETTING-UP PROCEDUREPreliminary PrecautionsBEFORE ATTEMPTING TO CONNECT POWER:-CONTROLLERCheck:-1. The Auxiliary Supply Voltage is correctly selected on the Power Board.2. The Main Power Supply Voltage is within the operating range of the controller.3. The Armature Voltage and current ratings are compatible with controller supplied.4. The Field Voltage and current ratings are suitable.5. All external wiring circuits are correct, i.e:- a) Auxiliary connectionsb) Power connectionsc) Control connectionsd) Motor connectionsNOTE: Completely disconnect the controller before point to point checking with a buzzer orwhen checking insulation with a megger.6. For damage to equipment.7. For loose ends, clippings, drilling swarf etc., lodged in the drive or ancillary equipment.MOTOR1. Inspect the motor, in particular the commutator for any extraneous matter. If an air supply isavailable, it is recommended to blow over the commutator.Check the brushes are properly seated and that the brush spring tension is adequate.If possible check that the motor (and vent fan if fitted) can be turned freely by hand.PreparationMACHINECheck:-1. That rotation of the motor in either direction will not cause damage.2. That nobody else is working on another part of the equipment that will be affected bypowering up.3. That other equipment will not be adversely affected by powering up.CONTROLLER1. Prevent application of the main power supply by removal of the supply fuses.2. Disconnect the load from the motor shaft if possible.3. If there is any doubt as to the integrity of a particular installation, insert a high wattageresistor (i.e. fire bar elements) in series with the motor armature.4. If it is possible to rotate the motor, and tachogenerator feedback is in use, check that forwardrotation results in positive tacho feedback, i.e. terminal 1 is positive with respect to terminal 8or 11.This manual was downloaded on www.sdsdrives.com+44 (0)117 938 1800 - info@sdsdrives.com