INSTALLING OPTIONS AND ACCESSORIESEaton 9395 550/275 UPS (225–550 kVA) Installation and Operation Manual 164201716 Rev 2 www.eaton.com/powerquality 5-11NOTE Setup of the Powerware Hot Sync CAN Bridge Card must be performed by an authorized EatonCustomer Service Engineer. Contact an Eaton service representative to schedule a date.13. To check the operation of the RMP II, ensure that the UPS is supplying the loadvia inverter or bypass. If the indicators on the RMP II show the appropriatestatus, then it is operating correctly.If the communication link between the UPS and the RMP II is not present, theRMP II performs a self‐test (all indicators flash and the horn beeps at one‐secondintervals). If the self-test occurs, check all harness connectors and the fuse forproper seating. If all connections are secure but the RMP II continues to self‐test,replace the fuse with the spare included in the hardware kit. If a fusereplacement does not correct the problem, contact an Eaton servicerepresentative for verification that the RMP II is working correctly.14. To test the indicator lamps, press and hold the horn silence pushbutton forthree seconds. All lamps should illuminate, and the horn sounds continuouslyuntil you release the pushbutton.5.4 Installing an Optional Relay Interface Module IITo install RIM II wiring:1. Verify the UPS system is turned off and all power sources are removed. SeeChapter 7, “UPS Operating Instructions,” for shutdown instructions.2. Perform the procedure listed in paragraph 5.1 on page 5-1.NOTE If mounting to a hollow wall, secure the enclosure to a wood or metal stud within the wall. Do notuse hollow wall anchors.3. Securely mount the RIM II at the desired location. See Figure 5‐13 on page 5-17for mounting hole locations.NOTE When installing signal wiring for CAN card J3 terminals, conduit must be installed between thedevice and the UPS cabinet.4. Remove the UPS cabinet top interface conduit landing plates to drill or punchconduit holes (see Figure 4‐4 on page 4-8).5. Reinstall the conduit landing plate.6. Install conduit between the UPS and RIM II. See Figure 5‐13 on page 5-17 forRIM II knockout hole location.7. Install wiring between the UPS and RIM II. See Figure 5‐2 and Table 5‐1 for thePowerware Hot Sync CAN Bridge Card terminal location and wiring information,and Figure 5‐7, Figure 5‐8, and Table 5‐5 for the RIM II terminal location andwiring information.NOTE 120 Vac for the RIM II should be supplied from the critical bus by facility planners or the customer.8. Install 120 Vac power wiring from the critical bus to the RIM II. See Figure 5‐7,Figure 5‐8, and Table 5‐5 for the terminal location and wiring information.9. Close the front door and secure the latch.