Product informationIntroductionEaton's Service Information MN280043EN providesassembly and installation instructions for its CooperPower™ series KNOVA59-1 and KNOVA59-3 substationframes. It contains a convenient step-by-step explanationof installation procedures as well as a parts list. Beforeassembling the frame, carefully read and understand thecontents of this manual.Read this manual firstRead and understand the contents of this manual and followall locally approved procedures and safety practices beforeinstalling or operating this equipment.Additional informationThese instructions cannot cover all details or variationsin the equipment, procedures, or process described norprovide directions for meeting every possible contingencyduring installation, operation, or maintenance. For additionalinformation, please contact your Eaton representative.Acceptance and initial inspectionAll frame parts are inspected at the factory. They are in goodcondition when accepted by the carrier for shipment.Upon receipt, inspect the shipping container for signsof damage. Unpack and inspect thoroughly for damageincurred during shipment. If damage is discovered, file aclaim with the carrier immediately.Handling and storageBe careful during handling and storage of the frame to mini-mize the possibility of damage. If the frame is to be storedfor any length of time prior to assembly or installation,provide a clean, dry storage area.Quality standardsISO 9001 Certified Quality Management SystemDescription of frameThe substation frame referenced in these instructions isintended for the following switchgear:• NOVA® Three-Phase, Microprocessor-Controlled Recloser• DAS Three-Phase, Vacuum-Break Distribution AutomationSwitch• VCS-3 Three-Phase, Vacuum-Break Capacitor Switch• TVS Time-Voltage Sectionalizer• NOVA STS Three-Phase, Microprocessor-ControlledRecloserThe galvanized frame is constructed of rigid structural orformed steel. The hardware is stainless steel. Practical,welded construction is used to provide a high degree ofrigidity with minimum weight. The substation frame heightis adjustable to satisfy a variety of application conditions.1SUBSTATION FRAME KNOVA59-1 AND KNOVA59-3 ASSEMBLY AND INSTALLATION INSTRUCTIONS MN280043EN January 2016