Eaton 93PM UPS (60–100 kW, 480V) Installation and Operation Manual P-164000227—Rev 2 www.eaton.com/powerquality 3-1Chapter 3 UPS Installation Plan and UnpackingUse the following basic sequence of steps to install the UPS:1. Create an installation plan for the UPS system (Chapter 3).2. Prepare your site for the UPS system (Chapter 3).3. Inspect and unpack the UPS cabinet (Chapter 3).4. Unload and install the UPS cabinet, and wire the system (Chapter 4).5. Install features, accessories, or options, as applicable (Chapter 4).6. Complete the Installation Checklist (Chapter 4).7. Have authorized service personnel perform preliminary operational checks and start up the system.3.1 Creating an Installation PlanBefore installing the UPS system, read and understand how this manual applies to the system being installed.Use the procedures and illustrations in paragraph 3.2 and Chapter 4 to create a logical plan for installing thesystem.3.2 Preparing the SiteFor the UPS system to operate at peak efficiency, the installation site should meet the environmentalparameters outlined in this manual. If the UPS is to be operated at an altitude higher than 1500m (5000 ft),contact an Eaton service representative for important information about high altitude operation. The operatingenvironment must meet the weight, clearance, and environmental requirements specified.3.2.1 Environmental and Installation ConsiderationsThe UPS system installation must meet the following guidelines:l The system must be installed on a level floor suitable for computer or electronic equipment.l The system must be installed in a temperature and humidity controlled indoor area free of conductivecontaminants.Failure to follow guidelines may void your warranty.The UPS equipment operating environment must meet the weight requirements shown in Table 3-1 and thesize requirements shown in Figure 3-1 through Figure 3-7. Dimensions are in millimeters (inches).NOTE Startup and operational checks must be performed by an authorized EatonCustomer Service Engineer, or the warranty terms specified on page W-1 becomevoid. This service is offered as part of the sales contract for the UPS. Contact anEaton service representative in advance (a minimum two-week notice is required)to reserve a preferred startup date.