UPS System Installation4-22 Eaton 93PM UPS (60–100 kW, 480V) Installation and Operation Manual P-164000227—Rev 2 www.eaton.com/powerquality4.10 Initial StartupStartup may be performed by the customer’s battery qualified electrical contractor for single (not parallel) UPSinstallations without any accessory cabinets such as an External Battery Cabinet.Startup and operational checks for parallel systems or installations with accessory cabinets must be performedby an authorized Eaton Customer Service Engineer, or the warranty terms specified on page W-1 become void.This service is offered as part of the sales contract for the UPS. Contact an Eaton service representative inadvance (usually a two-week notice is required) to reserve a preferred startup date.4.11 Completing the Installation ChecklistThe final step in installing the UPS system is completing the following Installation Checklist. This checklistensures that you have completely installed all hardware, cables, and other equipment. Complete all items listedon the checklist to ensure a smooth installation. Make a copy of the Installation Checklist before filling it out,and retain the original.After the installation is complete, an Eaton Customer Service Engineer must verify the operation of the UPSsystem and commission it to support the critical load. The service representative cannot perform anyinstallation tasks other than verifying software and operating setup parameters. Service personnel may requesta copy of the completed Installation Checklist to verify all applicable equipment installations have beencompleted.NOTE The Installation Checklist MUST be completed prior to starting the UPS system forthe first time.