InstallationEaton 93PM Integrated Battery Cabinet-Small Welded (IBC-SW) Installation Manual P-164000639—Rev 1 www.eaton.com/powerquality 4-254.5 Initial StartupStartup and operational checks must be performed by an authorized Eaton Customer Service Engineer, or thewarranty terms specified on page W-1 become void. This service is offered as part of the sales contract for theUPS. Contact an Eaton service representative in advance (a minimum two-week notice is required) to reservea preferred startup date.4.6 Completing the Installation ChecklistThe final step in installing the IBC–SW is completing the following Installation Checklist. This checklist ensuresthat you have completely installed all hardware, cables, and other equipment. Complete all items listed on thechecklist to ensure a smooth installation. Make a copy of the Installation Checklist before filling it out, and retainthe original.After the installation is complete, an Eaton Customer Service Engineer must verify the operation of the UPSsystem and commission it to support the critical load. The service representative cannot perform anyinstallation tasks other than verifying software and operating setup parameters. Service personnel may requesta copy of the completed Installation Checklist to verify all applicable equipment installations have beencompleted.Installation Checklisto All IBC–SWs are the same model and rating.o All packing materials and restraints have been removed from each cabinet.o The IBC–SWs are installed on a level floor suitable for computer or electronic equipment.o The IBC–SWs are placed in their installed locationo All conduits and cables are properly routed between the IBC–SWs and the UPS.o All power cables are properly sized and terminated.o A ground conductor is properly installed.o Battery cables are terminated on the positive and negative terminals in the UPS cabinet.o Battery Shunt trip and Battery Detect signal wiring is connected from the battery breaker to the UPS.o All internal safety shields are installed.o Air conditioning equipment is installed and operating correctly.o The area around the UPS system is clean and dust-free.o Adequate workspace exists around the IBC–SW and other cabinets.o Adequate lighting is provided around all IBC–SW and UPS equipment.o A 120 Vac service outlet is located within 7.5 meters (25 feet) of the IBC–SW and UPS equipment.o Startup and operational checks are performed by an authorized Eaton Customer Service Engineer.NOTE The Installation Checklist MUST be completed prior to starting the UPS system forthe first time.