Installing the UPS System3-15EATON Powerware® 9390 UPS (100–160 kVA) Installation and Operation Manual S 164201554 Rev E powerware.comInstallation Checklist- All packing materials and restraints have been removed from each cabinet.- Each cabinet in the UPS system is placed in its installed location.- The front shipping bracket is installed and adjusted, if the cabinet is not installed permanently.- A cabinet grounding/mounting kit is installed between any cabinets that are bolted together.- All conduits and cables are properly routed to the UPS and any ancillary cabinets.- All power cables are properly sized and terminated.- Neutral conductors are installed or bonded to ground as per requirements.- Battery cables are terminated on E4 (+) and E5 (-).- Battery UV trip and Aux contact signal wiring is connected from the UPS to the battery breaker.- LAN and telephone drops are installed.- All telephone and LAN connections have been completed.- A ground conductor is properly installed.- Air conditioning equipment is installed and operating correctly.- The area around the installed UPS system is clean and dust-free. (It is recommended that the UPS beinstalled on a level floor suitable for computer or electronic equipment.)- Adequate workspace exists around the UPS and other cabinets.- Adequate lighting is provided around all UPS equipment.- A 120 Vac service outlet is located within 7.5 meters (25 feet) of the UPS equipment.- The REPO device is mounted in its installed location and its wiring is terminated inside the UPS cabinet.The REPO switch must be a latching-type switch with a dedicated circuit.- The normally-closed (NC) Emergency Power-off contact (pins 1 and 2 on TB1) is jumpered if not used.- Alarm relays and building alarms are wired appropriately. (OPTIONAL)- A remote battery disconnect control is mounted in its installed location and its wiring is terminated insidethe UPS and battery cabinet. (OPTIONAL)- Accessories are mounted in installed locations and wiring is terminated inside the UPS cabinet.(OPTIONAL)- The debris shield covering the UPS cabinet ventilation grill is removed.- Startup and operational checks are performed by an authorized Eaton Customer Service Engineer.