Electrical installation 73Installing power and ground cables Further informationSee ACS580MV Base frame & TEU layout design for information on:• Project-specific cable entry• Distance between the point of cable entry and the termination bars• Busbar and fastening hole dimensions• Busbar designationsSee ACS580MV Wiring Diagram for information on:• Conventions for cross-references and device identification Preparing the cable entry and the cablesDetermining the cable length1 Determine the required length of a cable between the point of entry and the connectionpoint inside the cabinet.2 Cut the cable to the required length before connection.Preparing cables for entry plates• Prepare the cable termination as illustrated in the figure below.NOTICERisk of damage or malfunction!Waste inside the cabinet can cause damage or malfunction.If possible, do not cut cables inside the terminal compartment. Retrieve any waste whichaccidentally dropped into the cabinet.