UPS System InstallationEaton 93PM UPS (20–100 kW, 480V – 100 kW Frame) Installation and Operation Manual P-164000227—Rev 6 www.eaton.com/powerquality 4-134.11 Installing Interface ConnectionsUse the procedures in the following paragraphs to connect the customer and battery interface connections.4.11.1 Installing Building Alarm and Relay Contact ConnectionsTo install wiring:1. Verify the UPS system is turned off and all power sources are removed. See Chapter 6, “UPS OperatingInstructions,“ for shutdown instructions.2. If not already opened, open the front door by lifting the latch from the bottom and turning to the right(counterclockwise) and swing the door open.3. If wiring the interface terminals from the bottom of the UPS, proceed to Step 8; otherwise, proceed toStep 4.4. Top Entry Wiring. Remove the top interface entry conduit landing plates to drill or punch holes (seeFigure 4-4).5. Reinstall the interface entry plates and install the conduit.6. Route the UPS building alarm and relay output interface wiring through the top interface entry conduitlanding plates to the UPS building alarm and relay output terminals. See Figure 4-4 for wiring accessinformation, and Figure 4-9 and Figure 4-10 for UPS interface terminal locations.7. Proceed to Step 13.8. Bottom Entry Wiring. Remove the bottom interface entry conduit landing plates to drill or punch holes(see Figure 4-11).9. Reinstall the interface entry plates and install the conduit.10. Route the UPS building alarm and relay output interface wiring through the bottom interface entry conduitlanding plates to the bottom access interface wiring channel along the inside of the front door (seeFigure 4-11).11. Route the wiring along the interface wiring channel (see Figure 4-11) to the UPS building alarm and relayoutput terminals. See Figure 4-9 and Figure 4-10 for UPS interface terminal locations.12. Secure the wiring to the wire tie anchors provided (see Figure 4-12) using Zip ties.13. Connect the building alarm interface wiring to the building alarm terminals. See paragraph 3.2.4 andTable 4-1 for wiring and termination requirements, and Figure 4-13 for terminal assignments.14. Connect the relay output interface wiring to the relay output terminals. See paragraph 3.2.4 and Table 4-2for wiring and termination requirements, and Figure 4-14 for terminal assignments.NOTE If installing the IAC-D CT wiring, refer to the Eaton 93PM Integrated AccessoryCabinet-Distribution (50 kW, 100 kW, 150 kW, and 200 kW IAC-D) Installation andOperation Manual, listed in paragraph 1.8, for installation instructions.NOTE 1 If installing interface wiring connections between standalone cabinets or separatedevices, conduit must be installed between each cabinet or device.NOTE 2 Disconnect terminal block plugs from terminal blocks to wire plugs.