UPS System InstallationEaton 93PM UPS (20–100 kW, 480V – 100 kW Frame) Installation and Operation Manual P-164000227—Rev 6 www.eaton.com/powerquality 4-33Installation Checklisto All packing materials and restraints have been removed from each cabinet.o The UPS cabinet is placed in its installed location.o All conduits and cables are properly routed to the UPS and any ancillary cabinets.o All power cables are properly sized and terminated.o Battery cables are terminated on E4 (+) and E5 (–).o Battery shunt trip signal wiring is connected from the UPS to the battery disconnect.o Battery detect signal wiring is connected from the UPS to the battery disconnect.o A ground conductor is properly installed.o Building alarms and alarm relays are wired appropriately. (Optional)o LAN drops are installed. (Optional)o LAN connections have been completed. (Optional)o The REPO device is mounted in its installed location and its wiring is terminated inside theUPS cabinet. (Optional)o A jumper wire is connected between pins 3 and 4 on the REPO terminal block if using a normally-closedREPO switch. (Optional)o All internal safety shields are installed.o Accessories are mounted in installed locations and wiring is terminated inside the UPS cabinet. (Optional)o Air conditioning equipment is installed and operating correctly.o The area around the installed UPS system is clean and dust-free. (Eaton recommends that the UPS beinstalled on a level floor suitable for computer or electronic equipment.)o Adequate workspace exists around the UPS and other cabinets.o Adequate lighting is provided around all UPS equipment.o A 120 Vac service outlet is located within 7.5m (25 ft) of the UPS equipment.o Startup and operational checks are performed by an authorized Eaton Customer Service Engineer for parallelsystems or installations with accessory cabinets.