INSTALLING OPTIONS AND ACCESSORIESEaton Power Xpert 9395P-1200 UPS (1200 kVA, 1200 kW) Installation and Operation Manual P-164000500 Rev 4 www.eaton.com/powerquality5-45.2 Installing Distributed Bypass Control WiringNOTE When installing external wiring to the Powerware Hot Sync CAN Bridge Card, conduit must beinstalled to the UPS cabinet. When installing internal wiring to the Powerware Hot Sync CAN Bridge Cardterminals, route the wiring through the internal opening in the X-Slot communication bay.NOTE When installing interface wiring for the pull chain, conduit must be installed between UPSs.To install distributed bypass control wiring:1. Verify the UPS system is turned off and all power sources are removed. SeeChapter 7, “UPS Operating Instructions,” for shutdown instructions.2. Perform the procedure listed in paragraph 5.1.3. Terminal block TB3 is accessible on the left side of the X-Slot communication bay(see Figure 4‐21). To gain access to terminal block TB1, TB2, and the leftinterface entry conduit landing plates, remove the screws securing the topinternal safety shield panel and remove the panel. Retain the hardware for lateruse.4. Remove the interface entry conduit landing plates to drill or punch holes (seeFigure 4‐16).5. Reinstall the interface entry plates and install the conduit.6. To locate the appropriate terminals and review the wiring and terminationrequirements, see paragraph 3.2.4, Table 4‐1, and Figure 4‐21 throughFigure 4‐24.7. Route and install CAN wiring between the UPS cabinets. See Figure 5‐2 andTable 5‐1 for the Powerware Hot Sync CAN Bridge Card terminal location andFigure 5‐3, Figure 5‐4, and Table 5‐2 for wiring information.8. If a tie cabinet with Module Output Breakers (MOBs) is being wired, proceed toStep 11; otherwise, proceed to Step 9.9. Route and install distributed bypass system pull-chain wiring between the UPScabinets. See Figure 5‐5 and Table 5‐3 for wiring information.10. Proceed to Step 12.11. Route and install distributed bypass system pull-chain wiring between the UPScabinets and tie cabinet MOBs. See Figure 5‐6 and Table 5‐4 for wiringinformation.NOTE Setup of the Powerware Hot Sync CAN Bridge Card for parallel operation must be performed by anauthorized Eaton Customer Service Engineer. Contact an Eaton service representative to schedule a date.12. Reinstall the top internal safety shield panel and secure with the retainedhardware.13. Close the door and secure the latch.