UPS SYSTEM INSTALLATIONEaton Power Xpert 9395P-1200 UPS (1200 kVA, 1200 kW) Installation and Operation Manual P-164000500 Rev 4 www.eaton.com/powerquality4-2To prevent damage to the wiring channel and wiring in the UPM section base when lifting or moving thecabinet: Lift and move the UPM section using only the front or rear forklift slots. Verify that the forklift forks are in a horizontal position before inserting them into the forklift slots.DO NOT angle fork tips upward. Insert the forks all the way through the base. DO NOT insert forks partially into the base to move thecabinet. Forks may be partially inserted into the front or rear forklift slots for minor positioning if the forks arekept in a horizontal position with no upward angling. DO NOT use the forklift slots on the end of the cabinet to move the cabinet. End forklift slots may be used for minor positioning if the forks are kept in a horizontal position with noupward angling.If these instructions are not followed, damage to the wiring channel and wiring will occur.MISE EN GARDE! Ne pas incliner les armoires à plus de 10 degrés de la verticale. Ne soulever les armoires qu’à l’aide d’un chariot élévateur pour éviter de les endommager.Pour éviter d’endommager le câblage et son canal à la base de la section de l’onduleur lorsque l’armoire estsoulevée ou déplacée : Soulever ou déplacer la section de l’onduleur en n’utilisant que les passages de fourche à l’avant ou àl’arrière. Vérifier que les fourches du chariot élévateur sont en position horizontale avant de les insérer dans lespassages de fourche. NE PAS orienter les pointes de fourche vers le haut. Insérer complètement les fourches dans les passages de fourche de la base. NE PAS insérerpartiellement les fourches dans les passages pour déplacer l’armoire. Il est possible d’insérer partiellement les fourches dans les passages avant et arrière pour les petitsdéplacements, et ce, si les fourches sont en position horizontale sans pointer vers le haut. NE PAS utiliser les passages de fourche à l’extrémité de l’armoire pour la déplacer. Les passages de fourche à l’extrémité de l’armoire peuvent servir lors des petits déplacements, et ce, siles fourches sont en position horizontale sans pointer vers le haut. Si ces instructions ne sont pas suivies, des dommages au câblage et à son canal surviendront.NOTE For the following steps, verify that the forklift or pallet jack is rated to handle the weight of thecabinet (see Table 3‐1 for cabinet weight).1. If not already accomplished, use a forklift or pallet jack to move the ISBM andUPM sections to the installation area, or as close as possible, before unloadingfrom the pallets. If possible, move each section using the pallet. Insert the forkliftor pallet jack forks from the right side of the pallet (facing the cabinet), betweenthe supports on the bottom of the pallet (see Figure 3‐9 to Figure 3‐11 for theISBM and UPM section center of gravity measurements). If the sections must bemoved using the cabinet front or rear fork lift slots, see the caution statements atthe beginning of this procedure.2. Remove the three bolts securing the left side shipping bracket to the cabinet andthree bolts securing the bracket to the pallet (see Figure 4‐1 or Figure 4‐3).Remove the left side shipping bracket.3. Remove the three bolts securing the right side shipping bracket to the cabinetand three bolts securing the bracket to the pallet (see Figure 4‐2 or Figure 4‐4).Remove the right side shipping bracket.