Installing the Ergonomic WorkstationRoute CablesFollow these instructions for an overview on how to route cables through the assembledcomponents to a power source. These instructions are intended to provide general guidelinesonly since configurations may vary.To route cables, do the following:1. Route the power control cable from the power control switch (96239) through the channelin the workstation support frame to the control box (90066). When routing cables, adhereto these guidelines:a. The DL2 lift is to be connected to the sockets on the control box by means of themotor cables, which have a 6-pin plug in each end.b. The mains cable is to be mounted and power switched on. Please note that thecontrol box must only be connected to the voltage stated on the label.c. The control box earth cable should be mounted on the workstation in a way thatensures good electrical contact. The function of the earth cable is to earth thedesk and ground static electricity. The earth connection does not protect otherelectrical products.2. Route the power cable from the control box (90066) through the workstation supportframe, cable chain, and lower frame to a power outlet.See PortConnections DetailRefer to the following port connections illustration and perform the following instructions toconnect each cable to the appropriate port.29 Eaton Profile Genesys Dual-Lift Ergonomic Workstation Installation www.eaton.com/powerquality 11-41 06-2011