38 Eaton 93PM Integrated Accessory Cabinet-Tie (50 kW and 100 kW IAC-T) Installation and Operation Manual P-164000371—Rev 05Figure 11. Top and Bottom Conduit Landing Wire Entry LocationFrontTop ViewTop Access Conduit EntryLanding Plates for AC Inputand Outputt(Remove panel to drill orpunch conduit holes.)Bottom Access Conduit EntryLanding for AC Input andOutputt(Remove panel to drill orpunch conduit holes.)FrontBottom View9. Bottom Entry Wiring. Remove the bottom conduit plate (see Figure 11) from the inside bottom of theIAC-T. Identify all conduit requirements (both input and output) and mark their location. Drill and punch allconduit holes in the bottom conduit plate prior to mounting on the IAC-T. Install the conduit plate andinstall all conduit runs into the plate. Pull the wiring through conduit into the wiring area.10. Route the IAC-T MOB input cables (phase A, B, and C and Ground) from the UPS cabinets through thebottom of the IAC-T to the IAC-T MOB input terminals. See Figure 10 for IAC-T wiring access informationand Figure 12 for IAC-T terminal locations. See paragraph 3.2.2 IAC-T Power Wiring Preparation, Table 3,Table 4, or Table 5 for IAC-T wiring and termination requirements. Refer to the applicable Eaton 93PM UPSInstallation and Operation manual, listed in paragraph 1.7 For More Information, for the UPS terminallocations and termination requirements.11. Route the output cables (phase A, B, and C and Ground) from the IAC-T through the bottom of the cabinetto the critical load. See Figure 12 for IAC-T terminal locations. See paragraph3.2.2 IAC-T Power Wiring Preparation, Table 3, Table 4, or Table 5 for IAC-T wiring and terminationrequirements. Refer to the Eaton 93PM Integrated Accessory Cabinet-Distribution (50 kW, 100 kW, 150kW, and 200 kW IAC-D) Installation and Operation Manual, listed in paragraph 1.7 For More Information,for IAC-D conduit and terminal locations and termination requirements.12. Proceed to Step 16.13. Top Entry Wiring. Remove the top conduit plate (see Figure 11) from the top of the IAC-T. Identify allconduit requirements (both input and output) and mark their location. Drill and punch all conduit holes inthe top conduit plate prior to mounting on the IAC-T. Install the conduit plate and install all conduit runs intothe plate. Pull the wiring through the conduit into the wiring area.14. Route the IAC-T MOB input cables (phase A, B, and C and Ground) from the UPS cabinets through the topof the IAC-T to the IAC-T MOB input terminals. See Figure 10 for IAC-T wiring access information andFigure 12 for IAC-T terminal locations. See paragraph 3.2.2 IAC-T Power Wiring Preparation, Table 3,Table 4, or Table 5 for IAC-T wiring and termination requirements. Refer to the applicable Eaton 93PM UPSInstallation and Operation manual, listed in paragraph 1.7 For More Information, for the UPS terminallocations and termination requirements.15. Route the output cables (phase A, B, and C and Ground) from the IAC-T through the top of the cabinet tothe critical load. See Figure 12 for IAC-T terminal locations. See paragraphInstallation