Eaton 93PM Integrated Accessory Cabinet-Tie (50 kW and 100 kW IAC-T) Installation and Operation Manual P-164000371—Rev 05 43the top conduit plate prior to mounting on the IAC-T. Install the conduit plate and install all conduit runs intothe plate. Pull the wiring through the conduit into the wiring area.14. Route the IAC-T MOB input cables (phase A, B, and C and Ground) from the UPS cabinets through the topof the IAC-T to the IAC-T MOB input terminals. See Figure 10 for IAC-T wiring access information andFigure 15, Figure 16, or Figure 17 for IAC-T terminal locations. See paragraph3.2.2 IAC-T Power Wiring Preparation, Table 5, Table 6, or Table 7 for IAC-T wiring and terminationrequirements. Refer to the applicable Eaton 93PM UPS Installation and Operation manual, listed inparagraph 1.7 For More Information, for the UPS terminal locations and termination requirements.15. Route the output cables (phase A, B, and C and Ground) from the IAC-T through the top of the cabinet tothe critical load. See Figure 15, Figure 16, or Figure 17 for IAC-T terminal locations. See paragraph3.2.2 IAC-T Power Wiring Preparation, Table 5, Table 6, or Table 7 for IAC-T wiring and terminationrequirements. Refer to the Eaton 93PM Integrated Accessory Cabinet-Distribution (50 kW, 100 kW, 150kW, and 200 kW IAC-D) Installation and Operation Manual, listed in paragraph 1.7 For More Information,for IAC-D conduit and terminal locations and termination requirements..16. Connect MOB Ground, phase A, B, and C power wiring to the corresponding MOB input terminals on IAC-T.For a detailed view of the IAC-T MOB input terminals, see Figure 13.17. Connect the MOB Ground, phase A, B, and C power wiring from the IAC-T to the corresponding UPSpower terminals. Connect Ground, phase A, B, and C power wiring to the output terminals on the IAC-T.18. Connect the Ground, phase A, B, and C output power wiring from the IAC-T output terminals to the criticalload or Integrated Accessory Cabinet-Distribution (IAC-D).For a detailed view of the IAC-T output terminals, see Figure 18, Figure 19, or Figure 20.19. If wiring interface connections, proceed to paragraph 4.4 Installing IAC-T Interface Connections; otherwise,proceed to Step 20.20. Reinstall the internal safety shield panel removed in Step 3.21. Close the outside door and secure the latch.22. After the IAC-T is installed and wired, return to the applicable Eaton 93PM UPS Installation and Operationmanual, listed in paragraph 1.7 For More Information, to complete the UPS wiring.Installation