Eaton® Power Xpert® 9395P-1200 Installation and Operation Manual 164000500—Rev 11 15CChhaapptteerr 33 UUPPSS IInnssttaallllaattiioonn PPllaann aanndd UUnnppaacckkiinnggUse the following basic sequence of steps to install the UPS:1. Create an installation plan for the UPS system (Chapter 3).2. Prepare your site for the UPS system (Chapter 3).3. Inspect and unpack the UPS cabinet (Chapter 3).4. Unload and install the UPS cabinet, and wire the system (Chapter 4 UPS System Installation).5. Install features, accessories, or options, as applicable (Chapter 5 Installing Options and Accessories).6. Complete the Installation Checklist (Chapter 4 UPS System Installation).7. Have authorized service personnel perform preliminary operational checks and start up the system.NOTE Startup and operational checks must be performed by an authorized Eaton CustomerService Engineer, or the warranty terms specified on the Eaton website in section1.10 Warranty will become void. This service is offered as part of the sales contract forthe UPS. Contact an Eaton service representative in advance (usually a two-week noticeis required) to reserve a preferred startup date.33..11 CCrreeaattiinngg aann IInnssttaallllaattiioonn PPllaannBefore installing the UPS system, read and understand how this manual applies to the system being installed.Use the procedures and illustrations in paragraph 3.2 Preparing the Site and Chapter 4 to create a logical planfor installing the system.33..22 PPrreeppaarriinngg tthhee SSiitteeFor the UPS system to operate at peak efficiency, the installation site should meet the environmentalparameters outlined in this manual. If the UPS is to be operated at an altitude higher than 1000 m (3300 ft.),contact an Eaton service representative for important information about high altitude operation. The operatingenvironment must meet the weight, clearance, and environmental requirements specified.33..22..11 GGeenneerraall SSttoorraaggee RReeqquuiirreemmeennttss ffoorr UUPPSS EEqquuiippmmeenntt• Equipment which cannot be immediately installed and energized should be stored in an indoor, dry, clean,ventilated area, heated environment (i.e. an temperature and humidity controlled environment). Thestorage area must be protected from rain, water, chemical agents and gases as shown in Table 1.• Do not store in areas where conditions such as dampness, changes in temperature, dust, dirt, rubble,paint, conductive particulates, or corrosive atmosphere / gases are present.• Storage temperature: -25 °C to +60 °C (-13 °F to 140 °F).• Factory installed packaging and wrapping of the equipment should not be removed until equipment isready to install.• Equipment should be checked periodically for any signs of deterioration. It is the responsibility of thereceiving contractor to ensure protection during storage.• Equipment should be placed on true and solid level surfaces for storage.• Have a plan for condensation and environmental mitigation prior to equipment arrival.