Powering down/up applications (examples)Servicing the Network Management Module – 182••••••4.3.1.2 Step 1: Installation setup4.3.1.2.1 ObjectiveUse load segmentation provided by the UPS to independently control the power supply of each IT equipment categories(Applications, Database servers, Storage).It also allows IT equipment to sequentially restart on utility recovery (Restart sequentially the IT equipment on utility recovery).4.3.1.2.2 Resulting setupUPS provides outlets (Group 1 and Group 2) and a primary output.Connections to UPS are done as described below:Group 1: ApplicationsGroup 2: Database serversPrimary: Storage4.3.1.3 Step 2: Agent settings4.3.1.3.1 ObjectiveEnsure IT solution is shutdown gracefully.4.3.1.3.2 Resulting setup1. Install IPP Software on each server (Application, Database servers, Storage) and register the UPS load segment as power source:Applications: Group 1Database servers: Group 2Storage: Entire UPS2. Pair agent to the Network Module (Pairing agent to the Network Module).When done, each server appears in the Agent list.3. Navigate to Contextual help>>>Protection>>>Agent shutdown sequencing page.When primary shuts OFF, both group 1 and group 2 shut OFF immediately.For examples of Agent settings, see the Agent shutdown sequencing examples section.